Federal permitting decisions · Bureau of Land Management · data as of November 17, 2026

How long BLM takes to decide solar right-of-way applications

Of solar applications filed with the Bureau of Land Management in 2016–2020, 36% were decided within 12 months. Of those filed in 2021–2025, 12% were.

Almanac Grid is a free tracker of federal permitting outcomes, built from public agency records. This page covers BLM rights-of-way for solar, wind, transmission and pipelines, and geothermal leases.

Read this first

Full definitions, sources and exclusions are in Methodology.

Solar: decided within 12 months, by filing year

Filed 2016–2020
36%
36 of 100 decided within 12 months
Filed 2021–2025
12%
34 of 286 decided within 12 months
Share of solar applications decided within 12 months of filing
By year filed. n = applications filed that year with a recorded filing date.
0%
25%
50%
75%
100%
2016’16n=17
2017’17n=11
2018’18n=18
2019’19n=11
2020’20n=43
2021’21n=65
2022’22n=76
2023’23n=65
2024’24n=51
2025*’25*n=29

* 4 of the 29 applications filed in 2025 were filed after November 17, 2025, and have not yet had 12 months. 2026 filings are not shown.

Table
Year filedFiledDecided within 12 monthsShare
201617635.3%
20171119.1%
201818844.4%
201911436.4%
2020431739.5%
2021651320.0%
20227667.9%
202365710.8%
20245159.8%
202529310.3%

Solar applications past the §1402 deadline

Section 1402 of S.5653 would compare, for each project type, the share of applications pending more than 60 days past their deadline with the same share over that type's previous five years. Here the deadline is 1 year from filing, or 2 years for cases with an environmental impact statement (EIS). The chart shows that share for the open queue at the end of each year, next to the five previous years pooled.

End of 2025
84%
201 of 239 open applications overdue. Baseline 2020–2024: 61%
November 17, 2026
92%
215 of 235 open applications overdue. Baseline 2021–2025: 67%
Share of open solar applications more than 60 days past deadline
At year end. Baseline = the five previous year ends pooled (first available for 2021).
Overdue shareBaseline, previous 5 years
0%
25%
50%
75%
100%
92%67%
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026*

* 2026 is measured on November 17, not year end. Only 73 of 485 solar cases have a known review tier; the rest get the 1-year deadline, which counts some EIS-scale projects as overdue a year early.

Table
YearOpen at year endOverdueShareBaseline
2016614472.1%—
2017554378.2%—
2018594169.5%—
2019625385.5%—
2020814555.6%—
20211165144.0%71.1%
20221648451.2%62.5%
202319712362.4%56.8%
202422617477.0%57.4%
202523920184.1%60.8%
2026*23521591.5%67.2%

Decision timing by project type

The same 12-month measure for each BLM project type tracked here. Pipelines and transmission are limited to cases with an environmental assessment (EA) or EIS, which separates large projects from the many small lines in BLM's records.

Share decided within 12 months of filing, by year filed, 2016–2025
Same scale in every panel. Hover or focus a column for its numbers.

Solar

0%
50%
100%
2016’16
2025*’25*

Onshore wind

0%
50%
100%
2016’16
2025*’25*

1 to 5 filings a year: too few to read as a trend.

Geothermal leases

0%
50%
100%
2016’16
2025*’25*

Lease decisions, which come before (and are not) a power plant's permits.

Electric transmission, EA/EIS reviews

0%
50%
100%
2016’16
2025*’25*

Oil and gas pipelines, EA/EIS reviews

0%
50%
100%
2016’16
2025*’25*

All power-line rights-of-way

0%
50%
100%
2016’16
2025*’25*

BLM records can't separate transmission from distribution lines; most of these are small lines.

Table
Year filedSolarOnshore windGeothermal leasesElectric transmission, EA/EIS reviewsOil and gas pipelines, EA/EIS reviewsAll power-line rights-of-way
201635% (17)50% (2)100% (17)9% (11)29% (7)62% (435)
20179% (11)40% (5)100% (11)33% (15)57% (7)62% (342)
201844% (18)50% (2)86% (7)41% (17)50% (22)55% (396)
201936% (11)0% (2)100% (77)48% (23)95% (38)58% (407)
202040% (43)0% (3)99% (85)56% (25)89% (27)58% (395)
202120% (65)33% (3)100% (58)56% (23)75% (40)66% (305)
20228% (76)0% (3)99% (85)29% (14)68% (25)47% (350)
202311% (65)20% (5)100% (40)44% (25)76% (68)51% (312)
202410% (51)0% (4)97% (78)67% (45)89% (182)50% (364)
202510% (29)0% (1)100% (148)85% (34)94% (126)65% (298)

Applications filed 2016–2023: how long they took

Every application filed in these years has had at least 34 months. Median and middle half are for decided applications only; the ones still pending have taken longer than any of them.

Project typeFiledDecided ≤ 12 moDecided ≤ 24 moStill pendingMonths to decision: median (middle half)
Solar30620%32%48%17.7 (6.4–31.0)
Onshore wind2524%28%40%29.4 (6.9–41.1)
Geothermal leases38099%100%0%1.7 (0.9–2.5)
Electric transmission, EA/EIS reviews15343%67%7%12.8 (7.1–29.6)
Oil and gas pipelines, EA/EIS reviews23475%90%2%5.5 (3.4–10.0)
All power-line rights-of-way2,94258%74%8%8.0 (4.1–18.0)

How decisions ended, 2016–2026

Decisions dated 2016 through November 17, 2026, by outcome. "Closed, no reason recorded" are cases BLM closed without a grant, rejection or withdrawal in the record. Where that column is large, the rejected and withdrawn shares are lower bounds.

Project typeDecisionsGrantedRejectedWithdrawnClosed, no reason recorded
Solar22527%16%37%20%
Onshore wind3418%24%21%38%
Geothermal leases69495%1%0%4%
Electric transmission, EA/EIS reviews25792%1%5%3%
Oil and gas pipelines, EA/EIS reviews62595%0%4%1%
All power-line rights-of-way4,25378%2%11%10%

Methodology

Sources

All three are public. The data was last fetched on November 17, 2026.

Definitions

What's excluded

Snapshot

This page was built from a frozen snapshot of the database taken 2026-11-19, not from a live query. The snapshot's SHA-256 checksums:

8a8f0c4483573a48d2623497b9fd1282328d13bc37b754b73ed4e01b6273ec53 almanac_grid.dump 8de45afae51380e27c56010001833a18254f074589b5f67dff44cfa8f4175ee1 project.csv 35355d2576db4f1c6385a3bf4043a5713fa3427d89696e1d4a04286f2c6bce7b agency_action.csv cc6f6d26debc5518cc4b2395f080e352299dab4f1adc62f4b6855b5cdeab8d19 s1402_blm.json dce98da3b8c33cdab86dce96fe134685ecd2ac47555a6fff7570e56b361ef671 s1402_blm.txt

Every number on this page is also in figures.json.