Federal permitting decisions · Bureau of Land Management · data as of November 17, 2026
How long BLM takes to decide solar right-of-way applications
Of solar applications filed with the Bureau of Land Management in 2016–2020, 36% were decided within 12 months. Of those filed in 2021–2025, 12% were.
Almanac Grid is a free tracker of federal permitting outcomes, built from public agency records. This page covers BLM rights-of-way for solar, wind, transmission and pipelines, and geothermal leases.
Read this first
- The clock starts when an application arrived, not when it was complete. BLM records the date it received an application. It does not publish when an application was complete enough to process. Every elapsed time and overdue share on this page therefore overstates delay, by an unknown amount that may differ by project type and year.
- Solar and wind denial and withdrawal rates are lower bounds. BLM closed 20% of the solar decisions here, and 38% of the wind decisions, without recording a grant, rejection or withdrawal. Some of those were likely rejections or withdrawals.
- "Decided" means any final disposition: granted, rejected, withdrawn, or closed. It is not the same as approved.
- The numbers are small. 11 to 76 solar applications a year, and 1 to 5 for wind. A few cases move a year's percentage by several points.
- §1402 is part of a bill, S.5653, not law. The deadline comparison below applies the bill's test to past years. Under the bill only patterns after enactment would count, so these figures are not a finding under it.
Full definitions, sources and exclusions are in Methodology.
Solar: decided within 12 months, by filing year
* 4 of the 29 applications filed in 2025 were filed after November 17, 2025, and have not yet had 12 months. 2026 filings are not shown.
Table
| Year filed | Filed | Decided within 12 months | Share |
|---|---|---|---|
| 2016 | 17 | 6 | 35.3% |
| 2017 | 11 | 1 | 9.1% |
| 2018 | 18 | 8 | 44.4% |
| 2019 | 11 | 4 | 36.4% |
| 2020 | 43 | 17 | 39.5% |
| 2021 | 65 | 13 | 20.0% |
| 2022 | 76 | 6 | 7.9% |
| 2023 | 65 | 7 | 10.8% |
| 2024 | 51 | 5 | 9.8% |
| 2025 | 29 | 3 | 10.3% |
Solar applications past the §1402 deadline
Section 1402 of S.5653 would compare, for each project type, the share of applications pending more than 60 days past their deadline with the same share over that type's previous five years. Here the deadline is 1 year from filing, or 2 years for cases with an environmental impact statement (EIS). The chart shows that share for the open queue at the end of each year, next to the five previous years pooled.
* 2026 is measured on November 17, not year end. Only 73 of 485 solar cases have a known review tier; the rest get the 1-year deadline, which counts some EIS-scale projects as overdue a year early.
Table
| Year | Open at year end | Overdue | Share | Baseline |
|---|---|---|---|---|
| 2016 | 61 | 44 | 72.1% | — |
| 2017 | 55 | 43 | 78.2% | — |
| 2018 | 59 | 41 | 69.5% | — |
| 2019 | 62 | 53 | 85.5% | — |
| 2020 | 81 | 45 | 55.6% | — |
| 2021 | 116 | 51 | 44.0% | 71.1% |
| 2022 | 164 | 84 | 51.2% | 62.5% |
| 2023 | 197 | 123 | 62.4% | 56.8% |
| 2024 | 226 | 174 | 77.0% | 57.4% |
| 2025 | 239 | 201 | 84.1% | 60.8% |
| 2026* | 235 | 215 | 91.5% | 67.2% |
Decision timing by project type
The same 12-month measure for each BLM project type tracked here. Pipelines and transmission are limited to cases with an environmental assessment (EA) or EIS, which separates large projects from the many small lines in BLM's records.
Solar
Onshore wind
1 to 5 filings a year: too few to read as a trend.
Geothermal leases
Lease decisions, which come before (and are not) a power plant's permits.
Electric transmission, EA/EIS reviews
Oil and gas pipelines, EA/EIS reviews
All power-line rights-of-way
BLM records can't separate transmission from distribution lines; most of these are small lines.
Table
| Year filed | Solar | Onshore wind | Geothermal leases | Electric transmission, EA/EIS reviews | Oil and gas pipelines, EA/EIS reviews | All power-line rights-of-way |
|---|---|---|---|---|---|---|
| 2016 | 35% (17) | 50% (2) | 100% (17) | 9% (11) | 29% (7) | 62% (435) |
| 2017 | 9% (11) | 40% (5) | 100% (11) | 33% (15) | 57% (7) | 62% (342) |
| 2018 | 44% (18) | 50% (2) | 86% (7) | 41% (17) | 50% (22) | 55% (396) |
| 2019 | 36% (11) | 0% (2) | 100% (77) | 48% (23) | 95% (38) | 58% (407) |
| 2020 | 40% (43) | 0% (3) | 99% (85) | 56% (25) | 89% (27) | 58% (395) |
| 2021 | 20% (65) | 33% (3) | 100% (58) | 56% (23) | 75% (40) | 66% (305) |
| 2022 | 8% (76) | 0% (3) | 99% (85) | 29% (14) | 68% (25) | 47% (350) |
| 2023 | 11% (65) | 20% (5) | 100% (40) | 44% (25) | 76% (68) | 51% (312) |
| 2024 | 10% (51) | 0% (4) | 97% (78) | 67% (45) | 89% (182) | 50% (364) |
| 2025 | 10% (29) | 0% (1) | 100% (148) | 85% (34) | 94% (126) | 65% (298) |
Applications filed 2016–2023: how long they took
Every application filed in these years has had at least 34 months. Median and middle half are for decided applications only; the ones still pending have taken longer than any of them.
| Project type | Filed | Decided ≤ 12 mo | Decided ≤ 24 mo | Still pending | Months to decision: median (middle half) |
|---|---|---|---|---|---|
| Solar | 306 | 20% | 32% | 48% | 17.7 (6.4–31.0) |
| Onshore wind | 25 | 24% | 28% | 40% | 29.4 (6.9–41.1) |
| Geothermal leases | 380 | 99% | 100% | 0% | 1.7 (0.9–2.5) |
| Electric transmission, EA/EIS reviews | 153 | 43% | 67% | 7% | 12.8 (7.1–29.6) |
| Oil and gas pipelines, EA/EIS reviews | 234 | 75% | 90% | 2% | 5.5 (3.4–10.0) |
| All power-line rights-of-way | 2,942 | 58% | 74% | 8% | 8.0 (4.1–18.0) |
How decisions ended, 2016–2026
Decisions dated 2016 through November 17, 2026, by outcome. "Closed, no reason recorded" are cases BLM closed without a grant, rejection or withdrawal in the record. Where that column is large, the rejected and withdrawn shares are lower bounds.
| Project type | Decisions | Granted | Rejected | Withdrawn | Closed, no reason recorded |
|---|---|---|---|---|---|
| Solar | 225 | 27% | 16% | 37% | 20% |
| Onshore wind | 34 | 18% | 24% | 21% | 38% |
| Geothermal leases | 694 | 95% | 1% | 0% | 4% |
| Electric transmission, EA/EIS reviews | 257 | 92% | 1% | 5% | 3% |
| Oil and gas pipelines, EA/EIS reviews | 625 | 95% | 0% | 4% | 1% |
| All power-line rights-of-way | 4,253 | 78% | 2% | 11% | 10% |
Methodology
Sources
- BLM national case GIS layers for rights-of-way and geothermal leases: which cases exist, their product type, states and current disposition.
- BLM's Mineral & Land Records System (MLRS) case actions: the application date and the outcome, from BLM's own disposition action codes.
- BLM ePlanning (the National NEPA Register): the environmental review tier (categorical exclusion, EA or EIS), matched on case file number.
All three are public. The data was last fetched on November 17, 2026.
Definitions
- Filing date: the earliest "Application Received" action in MLRS, or "Case Established" if there is none. It is never estimated.
- Decision: the first action that grants, rejects or withdraws the application. A case closed without one is "closed, no reason recorded." Later amendments, renewals or relinquishments don't change it.
- Decided within 12 months: a final disposition of any kind within 365 days of the filing date, as a share of all applications filed that year with a filing date, including those still pending.
- Overdue: open more than 60 days past the deadline. Deadline = filing date plus 2 years for cases with an EIS, plus 1 year otherwise. §1402 counts from a complete application, which these records don't show.
- Baseline for a year: the five previous year-end open queues pooled (total overdue over total open).
- Review tier is known only where an ePlanning project lists the case. Cases without one are treated as non-EIS.
What's excluded
- Cases decided before 2016 are not loaded. Applications filed before 2016 appear only in the open-queue counts, if still open.
- Records whose decision date is in the future or before the filing date are dropped (Solar 1; Onshore wind 0; Geothermal leases 19; Electric transmission, EA/EIS reviews 0; Oil and gas pipelines, EA/EIS reviews 4).
- Cases with no filing date count in the outcome table but not in timing (Solar 36; Onshore wind 3; Geothermal leases 12; Electric transmission, EA/EIS reviews 4; Oil and gas pipelines, EA/EIS reviews 15).
- Some large projects are missing from BLM's GIS layers (presumably because their lands couldn't be mapped) and so aren't in the data.
- Wind and solar site-testing permits, temporary use permits and FERC decisions are not on this page.
Snapshot
This page was built from a frozen snapshot of the database taken 2026-11-19, not from a live query. The snapshot's SHA-256 checksums:
8a8f0c4483573a48d2623497b9fd1282328d13bc37b754b73ed4e01b6273ec53 almanac_grid.dump
8de45afae51380e27c56010001833a18254f074589b5f67dff44cfa8f4175ee1 project.csv
35355d2576db4f1c6385a3bf4043a5713fa3427d89696e1d4a04286f2c6bce7b agency_action.csv
cc6f6d26debc5518cc4b2395f080e352299dab4f1adc62f4b6855b5cdeab8d19 s1402_blm.json
dce98da3b8c33cdab86dce96fe134685ecd2ac47555a6fff7570e56b361ef671 s1402_blm.txt
Every number on this page is also in figures.json.